Haslemere Station Forecourt

Acting as principal contractor, Avon Construction were awarded the contract by South West Trains to provide various street works improvements to the enhance the safety of Haslemere Station forecourt.

The works package included realignment of kerb lines and crossing points, installation of street furniture, signs and safety barrier, casting of a new motorcycle parking slab, footpath construction and tarmac overlay and line marking to the existing forecourt surfacing.

Works at the station were carried out during normal daytime working hours, whilst maintaining public and transport access to the station forecourt at all times. Site activities were phased to ensure a smooth transition of works and to minimise disruption to local concessions. The forecourt surfacing works were programmed to be undertaken on a Sunday shift to coincide with the stations lowest foot flows and to reduce disruption.