Hartland Village Bridge

We are delighted to be working on the prestigious Hartland Village Entrance Bridge for St Edward Homes Ltd.

It is a design and build project to the value of £1.2m, with a contract duration of 6 months.

The main components of the build include reinforced concrete piles and foundations; precast concrete arches and walls; foam concrete infill over the arches; reinforced concrete bridge deck; block paving road construction; brick cladding and piers; copers; railings and lamp posts.

We are currently on target to complete the works before the Grand opening Ceremony in September.